The steps
- Gather the set. Grading plan, existing topo, geotech report, and the paving and building sections.
- Check the scale. Measure a known dimension on the PDF before you trust the scale bar.
- Set the limits. Mark the limits of grading, the phases and any separate bid items.
- Build existing ground from the existing contours and spot elevations.
- Strip topsoil. Lower existing ground by the stripping depth in the geotech report.
- Build finished grade from the design contours, spot elevations, curbs and pads.
- Drop to subgrade. Subtract the pavement section, slabs and base. The dirt crew builds to subgrade, not finished grade.
- Measure the difference. Where subgrade is below the stripped ground it is cut. Where it is above, it is fill.
- Apply shrink and swell to get import or export. See the swell and shrink factors.
- Check the result. The cut and fill areas should add up to the graded area, and the cut/fill map should look like the site.
Mistakes that move the number
- Measuring to finished grade when the crew builds to subgrade
- Skipping topsoil stripping
- Leaving out over-excavation called for in the geotech report
- Mixing bank, loose and compacted yards
- Trusting a PDF that was printed to fit the page, which changes the scale
- Missing offsite grading where the site ties in to the street
When to hand it off
If the bid is due and the set is large, we do this as a service. Takeoffs start at $450 and are delivered in 3 to 5 business days.
Send the plans, get a price
Quotes are free and come before any work starts. Delivery is 3 to 5 business days, nationwide.