The three states of dirt
- Bank cubic yards (BCY) are measured in the ground, before digging. Plans and takeoffs measure cut in bank yards
- Loose cubic yards (LCY) are measured after digging. Soil swells when it is broken up, and trucks haul loose yards
- Compacted cubic yards (CCY) are measured after the soil is placed and compacted. Fill is measured in compacted yards
Typical factors by material
| Material | Bank to loose | Bank to compacted | Swell | Change when compacted |
|---|---|---|---|---|
| Sand or gravel | 1.11 | 0.95 | 11% | Shrinks 5% |
| Loam (common earth) | 1.25 | 0.90 | 25% | Shrinks 10% |
| Clay | 1.43 | 0.90 | 43% | Shrinks 10% |
| Rock, blasted | 1.50 | 1.30 | 50% | Grows 30% |
Source: U.S. Army Field Manual 5-434, Earthmoving Operations, Table 1-1. These are typical values. When your geotech report gives shrink and swell for the site, use those.
The formulas
- Loose CY = bank CY x (1 + swell)
- Compacted CY = bank CY x (1 - shrink)
- Bank CY needed for a fill = compacted CY / (1 - shrink)
- Load factor = 1 / (1 + swell)
Worked example
You cut 1,000 bank cubic yards of common earth. Loaded in trucks it is 1,000 x 1.25 = 1,250 loose cubic yards. Placed and compacted as fill it is 1,000 x 0.90 = 900 compacted cubic yards.