Grid method
Lay a grid over the site. At each grid corner, take the cut or fill depth. For each cell, average the four corner depths and multiply by the cell area.
- Volume of a cell = cell area x (d1 + d2 + d3 + d4) / 4
Example: a 50 ft by 50 ft cell with corner cuts of 1.0, 2.0, 1.5 and 0.5 ft averages 1.25 ft. 2,500 sq ft x 1.25 ft = 3,125 cubic feet, or 115.7 cubic yards. A smaller grid follows the ground better and takes longer.
Average end area
Used for roads, channels and levees. Take the cut or fill area on a cross section at each station, average two neighbors and multiply by the distance between them.
- Volume = distance x (A1 + A2) / 2
Example: two sections 100 ft apart with cut areas of 120 and 180 sq ft give 100 x 150 = 15,000 cubic feet, or 555.6 cubic yards. The method runs high when the two end areas are very different.
Prismoidal
The same cross sections, plus a section at the midpoint. It is closer than average end area when the shape changes between stations.
- Volume = distance / 6 x (A1 + 4 x Am + A2)
Surface to surface
Software builds existing ground and the design as two surfaces of triangles and measures the volume between them. This is how takeoff software such as AGTEK works, and it follows the ground better than any hand method.
Which one to use
| Method | Best for | What you need |
|---|---|---|
| Grid | Pads, lots and small sites | Existing and design grades at each grid corner |
| Average end area | Roads, channels and levees | Cross sections at regular stations |
| Prismoidal | The same, where sections change shape | Cross sections plus a middle section |
| Surface to surface | Any site | Existing and design surfaces |